Posts

Showing posts from July, 2018

Primavera

Image
Project managers needs a smart tool to plan their projects. Usually the planing phase requires lots of work and care to not fall in mistakes. Therefore, there was the need for a simple software that can help project managers plan their projects. Here I will be discuss the main parts of Primavera course that I took under Dr. Ehab Soliman in Handis Academy. The course explained Setting up, Activities, Work Breakdown Structure, Construction Specification Institute, Resources, Print and Save, and Data Analyses.   Setting up the Primavera Before starting the CPM, first we need to setup the program parameters; such as, time and currency. To do so, click “Edit” from the tool bar, then “User Performance” as shown bellow in Figure(1). Figure (1): User Performance. After clicking “User Performance” the next window will come out in Figure (2). From this window we will consider the first three options on the left side. The option “Time Units” is shown below. In this option we can